Required permits and time limits for issuing them
3 days – issuing a Planning Act reference statement
3 days – harmonization of the Project with the Planning Act reference statement
7 days – issuing a decision on approving construction
2 days – registration of construction works
7 days – technical admittance of the facility and issuing a utilization permit for the facility
NOTE: At the investors service is a Municipal Service Team of 4 members that help the investors to acquire approval from public companies and other institutions.
|